Toyota Motor Engineering & Manufacturing North America, Inc. (TEMA) plans to adjust production in May due to parts availability following the March 11 Japan earthquake and tsunami.

Previously, TEMA had announced production suspensions on Mondays and Fridays during the period April 15 through April 25. TEMA will continue the Monday and Friday production suspension pattern during the period April 26-June 3. During the same period, production will run at 50 percent on Tuesday, Wednesday and Thursday.

Additionally, Canadian production will be suspended the week of May 23 (in conjunction with the scheduled Victoria Day holiday) and U.S. production will be suspended the week of May 30 (in conjunction with the scheduled Memorial Day holiday).

No layoffs are planned during this period. Team members will utilize non-production time for training and plant improvement activities.

"We are trying to continue production as much as possible and keep our workforce intact in order to facilitate a smooth transition back to full production when all parts are available," said Steve St. Angelo, executive vice president of TEMA.

Production plans beyond June 3 will be determined at a later date.



2011 New York Auto Show Photo Gallery

New York Auto Show Preview Photo Gallery

2012 Audi A7 USA Model Photo Gallery

Lexus LF-Gh Concept Photo Gallery

2012 Audi Q3 Photo Gallery


AutoSpies.com Photo Galleries

If you want to see your photos running on our homepage photo ticker, be sure to upload your photos on the go by sending them to Mobile@AutoSpies.com

Share on Facebook





Failure Of Toyota's Just In Time Supply Chain Severly Limits Production To June And Beyond

About the Author

Agent009